Home›Concrete Mix Ratio Calculator

Concrete Mix Ratio Calculator

A mix ratio is a recipe, not a guess: one part cement, two parts sand, three parts gravel makes a different concrete from one-two-four, and the water decides the strength more than the cement does. Enter the volume and the ratio to get the bags, the sand, the gravel and the water — plus the one-bag batch you actually work from at the mixer.

Calculate a concrete mix

Units:

Your results

45.74 cu ft
dry material
8 bags
cement bags
15.25 cu ft
sand
22.87 cu ft
gravel
45.1 gal
starting water
$165
estimated cost

How the concrete mix formula works

Dry volume = wet volume × 1.54  ·  Each material = dry volume × its parts ÷ total parts  ·  Bags = cement cu ft ÷ bag volume, rounded up  ·  Water (gal) = cement lb × water-cement ratio ÷ 8.34

The unobvious step is the dry-volume factor: dry materials take up more space than the concrete they make, because sand fills the voids between the gravel and cement paste fills the gaps around the sand — so 1 cubic yard of wet concrete needs 1.54 × 27 = 41.58 cu ft of dry material (measureandbuild.com, buildingsmath.com, calcwall.com — all three agree). That dry volume is split by the ratio parts: at 1:2:3 the cement is 1/6, the sand 2/6, the gravel 3/6. A 94 lb sack of Portland cement is about 1 cu ft, so the cement cubic feet are the bag count. Water follows the cement, not the total volume: at a 0.50 water-cement ratio, half the cement weight in water — 94 lb × 0.50 ÷ 8.34 lb/gal = 5.6 gal per bag. The strengths are nominal, not guaranteed: actual strength depends on aggregate quality, water content, compaction, curing and temperature. Above a 0.68 water-cement ratio the ACI 211.1 table puts the mix under 3,000 psi.

Worked example

Worked example: 1 cubic yard at 1:2:3, 10% waste

One cubic yard of wet concrete at 1:2:3 (3,000 psi nominal), 10% waste, 1.54 dry factor, 0.50 water-cement ratio, 94 lb bags:

Cross-check: buildingsmath.com gives the same arithmetic at 0% waste — 7 bags, 13.86 cu ft of sand, 20.79 cu ft of gravel and about 39 gal of water for 1 cubic yard at 1:2:3 — and this calculator matches all four numbers at 0% waste. The one-bag batch: 1 bag of cement + 2.0 cu ft sand + 3.0 cu ft gravel + 5.6 gal water, making about 3.9 cu ft. A second check at 1:2:4: 2 cubic yards at 10% waste needs 14 bags, 26.14 cu ft of sand and 52.27 cu ft of gravel.

A ratio is a rule of thumb, not a mix design. Footings under beams and anything an inspector will look at should follow a specified mix design (ACI 211.1), not a bench ratio.

How much does site-mixed concrete cost? (US, 2026)

Typical 2026 US prices. Site mixing beats premixed bags on anything over about half a yard; ready-mix beats site mixing over about 2-3 yards.

ItemTypical cost (US, 2026)
Portland cement, 94 lb bag$12-$15
Sand, per cu yd$35-$45
Gravel, per cu yd$40-$50
Premixed 80 lb bag (for comparison)$6-$8
1 cu yd at 1:2:3, site-mixed~$165
1 cu yd at 1:2:3, premixed bags~$315
US 2026 prices, checked November 2026. Sources: measureandbuild.com concrete mix calculator, buildingsmath.com concrete mix calculator, calcwall.com mix ratio calculator, US retail listings.

Waste allowance

The waste allowance covers spillage at the mixer, the material left in the wheelbarrow and the forms, and the odd over-pour. Ten percent is the standard for site-mixed concrete; use 5% on a small, well-formed pour and 15% where the subgrade is uneven or the forms are leaky.

Frequently asked questions

What concrete mix ratio should I use for a driveway?

1:1.5:3, about 4,000 psi nominal — driveways and garage slabs carry heavy vehicle loads. General-purpose work (patios, paths, shed floors) uses 1:2:3 at about 3,000 psi; footings and non-structural fill use 1:2:4 at about 2,500 psi.

What is the dry volume factor 1.54?

Dry materials take up more space than the concrete they make: sand fills the voids between the gravel, and cement paste fills the gaps around the sand. So 1 cubic yard of wet concrete needs 41.58 cu ft of dry material — 1.54 times the finished volume. All three reference calculators use 1.54.

How much water do I add to a concrete mix?

Start at a 0.50 water-cement ratio by weight: half the cement weight in water, about 5.6 gallons per 94 lb bag. The cement needs only about 0.22-0.25 of its weight to hydrate — the rest is for workability, and every extra gallon weakens the concrete. Add water gradually and stop when the mix is workable.

Can I use a 1:2:3 mix for footings?

For non-structural footings, garden walls and posts, yes. For footings under beams, columns and anything an inspector will look at, follow a specified mix design (ACI 211.1) — a bench ratio is not an engineered mix, and the strength figures here are nominal, not guaranteed.

How many bags of cement per cubic yard?

At 1:2:3, about 7 bags of 94 lb cement per cubic yard before waste (8 with 10% waste). At 1:1:2 it is about 10.4 bags; at 1:2:4 about 5.9; at 1:3:6 about 4.2. The richer the mix, the more cement per yard.