Gravel Driveway Calculator
Work out how much gravel a driveway needs — the compacted base layer underneath and the top layer you actually drive on — in cubic yards and tons, with the cost. A new driveway needs both layers; a top-up needs only the top one. The tons come from the volume times the stone’s density, which is why different gravel types weigh differently for the same volume.
Calculate your gravel driveway
A new driveway needs a 4–8 in base of large aggregate and a 2–4 in top layer of smaller stone. The base is 1.35 tons per cubic yard for ABC, 1.38 for #57, 1.40 for limestone, 1.35 for pea gravel and 1.30 for river rock.
Your results
How the gravel driveway formula works
Two layers, two volumes, two densities. The base is large aggregate that locks together; the top is smaller stone that compacts into a smooth driving surface.
Base volume: length × width × base depth ÷ 12 ÷ 27 in cubic yards
Top volume: length × width × top depth ÷ 12 ÷ 27 in cubic yards
Tons: volume × density × (1 + waste)
Densities: ABC 1.35, #57 1.38, limestone 1.40, pea gravel 1.35, river rock 1.30 t/yd³
Cost: base tons × $35 + top tons × $45
This is the CalculateGravel / YourSEOTools method, and it reproduces their published examples: a 100 × 12 ft driveway, 4 in of ABC base and 2 in of #57 top, 10% waste — 14.81 yd³ of base (22.0 tons) and 7.41 yd³ of top (11.2 tons), 33.2 tons total, $1,276; a 40 × 12 ft top-up, 4 in of limestone at 1.40 t/yd³ — 5.93 yd³, 9.13 tons (YourSEOTools). The pre-waste volumes agree with CalculateGravel’s published figures (20.0 tons of base and 10.2 tons of top before the 10% allowance).
Worked example
A 100 × 12 ft new driveway, 4 in of ABC base, 2 in of #57 top, 10% waste:
Base volume: 100 × 12 × 4 ÷ 12 ÷ 27 = 14.81 yd³ · Tons: 14.81 × 1.35 × 1.10 = 22.0 tons
Top volume: 100 × 12 × 2 ÷ 12 ÷ 27 = 7.41 yd³ · Tons: 7.41 × 1.38 × 1.10 = 11.2 tons
Total: 33.2 tons · Cost: 22.00 × $35 + 11.24 × $45 = $770 + $506 = $1,276 — about $1.06 per sq ft
For a 40 × 12 ft top-up, 4 in of limestone at 1.40 t/yd³, 10% waste: 5.93 yd³, 9.13 tons, $411. And a 50 × 10 ft new driveway, 6 in of base, 3 in of top, 15% waste: base 9.26 yd³ → 14.4 tons, top 4.63 yd³ → 7.3 tons, total 21.7 tons, $834.
How much does a gravel driveway cost? (US, 2026)
Prices are 2026 US ranges from HomeGuide and HomeAdvisor. Delivered prices vary by distance — a quarry 20 miles away can double the haulage. Check local prices before ordering.
| Item | Typical price |
|---|---|
| ABC / crusher run, delivered | $30–$40 per ton |
| #57 stone, delivered | $40–$50 per ton |
| Limestone, delivered | $40–$55 per ton |
| Pea gravel, delivered | $35–$50 per ton |
| Excavation & grading | $2–$5 per sq ft |
| Plate compactor rental | $60–$100 per day |
| Pro-installed gravel driveway | $2–$6 per sq ft |
Waste allowance
10% is the standard allowance for settling, spreading and the stone that works its way into the ground on soft soil. Use 5% only on firm, well-compacted ground, and 15% on soft or wet ground where the first load disappears into the subgrade. Top-ups need less waste than a new driveway, because the base is already there.
Frequently asked questions
How much gravel do I need for a 100 ft driveway?
About 33.2 tons for a 100 × 12 ft driveway with a 4 in ABC base and a 2 in #57 top — 22.0 tons of base and 11.2 tons of top, at a cost of about $1,276. For a 10 ft wide driveway it is about 27.7 tons.
How many tons of gravel for a driveway?
About 1.7 tons per 100 square feet for a 4 in layer. A 40 × 12 ft driveway with a 4 in top-up needs about 9.13 tons of limestone; the same driveway built from scratch needs about 8.8 tons of base plus 4.5 tons of top.
How deep should a gravel driveway be?
A 4–8 in base of large aggregate plus a 2–4 in top layer of smaller stone — 6–12 in in total. Use 4 in of base and 2 in of top for light use, and 8 in of base and 4 in of top for heavy trucks.
How much does a gravel driveway cost?
About $1,276 for a 100 × 12 ft driveway, materials only ($35 per ton for the base, $45 for the top). A pro-installed gravel driveway runs $2–$6 per square foot — about $2,400–$7,200 for the same driveway.
How long does a gravel driveway last?
20–30 years with a proper base and a fresh top layer every 2–3 years. The base is permanent; only the top layer wears away, which is why top-ups are the normal maintenance.