Excavation Cost Calculator
A homeowner hears two prices that look contradictory. Some guides quote $2.50-$15 per cubic yard — the digging alone, before mobilisation, disposal or equipment is added. Others quote $50-$200 per cubic yard, the all-in price. Both are right about the part they cover. This calculator uses the all-in per-yard rates, because a homeowner pays the whole job, not the digging alone: $40-$120 per cubic yard depending on the work, with access and soil factors, haul-off, mobilisation and the truck count on top.
Calculate excavation cost
Your results
How the excavation cost formula works
Volume = L × W × D ÷ 27 (bank yd³) · Digging = volume × rate × access × soil · Haul-off = volume × $18 · Total = digging + haul-off + mobilisation · Loose volume = bank × 1.25 · Loads = ceil(loose ÷ 14)
Digging is priced all-in per cubic yard by job type (published US 2026 cost guides): site grading $40, trenching $60, foundation $75, basement $105, pool $120, each the midpoint of the published 2026 bands. Access scales the rate — open is 1.0, moderate 1.16 and tight 1.35 — because restricted access means smaller machines and hand work. Soil scales it too: normal is 1.0, heavy clay 1.25 and rock 2.0, with blasting extra. Haul-off is $18 a bank cubic yard and applies when the soil leaves site; when it stays on site as backfill the haul line drops to zero. Mobilisation is a flat $500 by default, the $350-$800 published band. Loose volume is the bank volume times a 1.25 swell factor, and loads are the loose volume divided by a 14 yd³ truck, rounded up with a float-safe ceiling.
Worked example
Worked example: 30 × 40 ft basement, 8 ft deep
A basement excavation 30 ft by 40 ft and 8 ft deep, open access, normal soil, haul-off on:
- Bank volume: 30 × 40 × 8 ÷ 27 = 355.56 yd³
- Digging: 355.56 × $105 = $37,333.80
- Haul-off: 355.56 × $18 = $6,400.08
- Mobilisation: $500.00 → total $44,233.88 — $124.41 per yd³ all-in
- Loose volume: 355.56 × 1.25 = 444.45 yd³ → 32 loads at 14 yd³
Cross-check: an independent cost guide prices a 300-400 yd³ basement at $25,000-$50,000 — $44,233.88 sits inside that band. A second check, a 150 yd³ foundation with moderate access and haul-off: 150 × $75 × 1.16 = $13,050 + $2,700 + $500 = $16,250.00, against an independent cost guide's $16,100 — 0.9% over, because this calculator uses $500 mobilisation where their example uses $350. A third: a 24 × 24 ft garage pad, 1.5 ft deep, grading rate, open access, no haul-off — 32 yd³ × $40 = $1,280 + $500 = $1,780.00, inside HomeGuide most-jobs band of $1,100-$5,600.
An estimate, not a quote. Excavation is usually billed as a lump sum for the whole job rather than per yard, and rock, groundwater, buried utilities or a tight site can push the real price far above the per-yard bands. Call 811 before you dig.
How much does excavation cost? (US, 2026)
All-in rates by job type, checked November 2026. The typical excavation project runs $1,100-$5,600 (HomeGuide), with a national average near $3,100-$3,500.
| Job type | All-in rate per yd³ (US, 2026) | Calculator rate |
|---|---|---|
| Site grading | $30 – $55 | $40 |
| Trenching | $45 – $80 | $60 |
| Foundation excavation | $60 – $100 | $75 |
| Basement excavation | $80 – $130 | $105 |
| Pool excavation | $90 – $150 | $120 |
| Digging only (no mobilisation or haul-off) | $2.50 – $15 | — |
| Haul-off | $10 – $25 per yd³ | $18 |
| Mobilisation & equipment | $350 – $800 | $500 |
| Swell factor (bank to loose) | ×1.25 | ×1.25 |
| Rock multiplier | ×1.5 – ×2.5 | ×2.0 |
| Typical project range | $1,100 – $5,600 | — |
| US 2026 prices, checked November 2026. Sources: HomeGuide, Angi, thepricer.org, lawnlove.com, mulchdeck.com. | ||
Waste allowance
There is no waste percentage on excavation — the allowance to plan for is the swell. Soil occupies about 25% more volume once it is loose than it did in the ground, and the truck count is based on the loose volume, not the bank volume. A job that looks like 25 loads on the bank figure is 32 loads on the truck figure.
Frequently asked questions
How much does excavation cost per cubic yard?
All-in, $50-$200 per cubic yard depending on the job: grading $40, trenching $60, foundation $75, basement $105, pool $120. The $2.50-$15 figures you see quoted elsewhere are digging only, before mobilisation, haul-off or equipment — the same job, priced two ways. This calculator prices the all-in job.
How many cubic yards of soil does a basement take out?
A 30 × 40 ft basement 8 ft deep is 355.56 bank yd³ in the ground, or 444.45 loose yd³ once dug — 32 truck loads at 14 yd³ each. The loose volume is about 25% more than the bank volume, and the truck count is based on the loose figure.
Why is rock excavation so expensive?
Because it needs a breaker, a ripper or blasting instead of a bucket, and the machine time roughly doubles. This calculator uses a ×2.0 multiplier for rock, inside the published ×1.5-×2.5 band; blasting is an extra line on top.
Is excavation billed by the yard or by the job?
Usually as a lump sum for the whole job, with the per-yard rates used to build the quote. A small job costs far more per yard than a large one because mobilisation and equipment delivery are fixed.
Do I need to call 811 before digging?
Yes — call 811 or your local one-call centre at least two business days before digging, so buried utilities are marked. It is free, and digging into a gas or electric line is the most expensive mistake on the job.