Excavation Cost Calculator

A homeowner hears two prices that look contradictory. Some guides quote $2.50-$15 per cubic yard — the digging alone, before mobilisation, disposal or equipment is added. Others quote $50-$200 per cubic yard, the all-in price. Both are right about the part they cover. This calculator uses the all-in per-yard rates, because a homeowner pays the whole job, not the digging alone: $40-$120 per cubic yard depending on the work, with access and soil factors, haul-off, mobilisation and the truck count on top.

Calculate excavation cost

Units:

Your results

355.56
bank volume (yd³)
$37,333.80
digging cost
$6,400.08
haul-off cost
$500.00
mobilisation
$44,233.88
total excavation cost
32 loads
14 yd³ trucks

How the excavation cost formula works

Volume = L × W × D ÷ 27 (bank yd³)  ·  Digging = volume × rate × access × soil  ·  Haul-off = volume × $18  ·  Total = digging + haul-off + mobilisation  ·  Loose volume = bank × 1.25  ·  Loads = ceil(loose ÷ 14)

Digging is priced all-in per cubic yard by job type (published US 2026 cost guides): site grading $40, trenching $60, foundation $75, basement $105, pool $120, each the midpoint of the published 2026 bands. Access scales the rate — open is 1.0, moderate 1.16 and tight 1.35 — because restricted access means smaller machines and hand work. Soil scales it too: normal is 1.0, heavy clay 1.25 and rock 2.0, with blasting extra. Haul-off is $18 a bank cubic yard and applies when the soil leaves site; when it stays on site as backfill the haul line drops to zero. Mobilisation is a flat $500 by default, the $350-$800 published band. Loose volume is the bank volume times a 1.25 swell factor, and loads are the loose volume divided by a 14 yd³ truck, rounded up with a float-safe ceiling.

Worked example

Worked example: 30 × 40 ft basement, 8 ft deep

A basement excavation 30 ft by 40 ft and 8 ft deep, open access, normal soil, haul-off on:

Cross-check: an independent cost guide prices a 300-400 yd³ basement at $25,000-$50,000 — $44,233.88 sits inside that band. A second check, a 150 yd³ foundation with moderate access and haul-off: 150 × $75 × 1.16 = $13,050 + $2,700 + $500 = $16,250.00, against an independent cost guide's $16,100 — 0.9% over, because this calculator uses $500 mobilisation where their example uses $350. A third: a 24 × 24 ft garage pad, 1.5 ft deep, grading rate, open access, no haul-off — 32 yd³ × $40 = $1,280 + $500 = $1,780.00, inside HomeGuide most-jobs band of $1,100-$5,600.

An estimate, not a quote. Excavation is usually billed as a lump sum for the whole job rather than per yard, and rock, groundwater, buried utilities or a tight site can push the real price far above the per-yard bands. Call 811 before you dig.

How much does excavation cost? (US, 2026)

All-in rates by job type, checked November 2026. The typical excavation project runs $1,100-$5,600 (HomeGuide), with a national average near $3,100-$3,500.

Job typeAll-in rate per yd³ (US, 2026)Calculator rate
Site grading$30 – $55$40
Trenching$45 – $80$60
Foundation excavation$60 – $100$75
Basement excavation$80 – $130$105
Pool excavation$90 – $150$120
Digging only (no mobilisation or haul-off)$2.50 – $15—
Haul-off$10 – $25 per yd³$18
Mobilisation & equipment$350 – $800$500
Swell factor (bank to loose)×1.25×1.25
Rock multiplier×1.5 – ×2.5×2.0
Typical project range$1,100 – $5,600—
US 2026 prices, checked November 2026. Sources: HomeGuide, Angi, thepricer.org, lawnlove.com, mulchdeck.com.

Waste allowance

There is no waste percentage on excavation — the allowance to plan for is the swell. Soil occupies about 25% more volume once it is loose than it did in the ground, and the truck count is based on the loose volume, not the bank volume. A job that looks like 25 loads on the bank figure is 32 loads on the truck figure.

Frequently asked questions

How much does excavation cost per cubic yard?

All-in, $50-$200 per cubic yard depending on the job: grading $40, trenching $60, foundation $75, basement $105, pool $120. The $2.50-$15 figures you see quoted elsewhere are digging only, before mobilisation, haul-off or equipment — the same job, priced two ways. This calculator prices the all-in job.

How many cubic yards of soil does a basement take out?

A 30 × 40 ft basement 8 ft deep is 355.56 bank yd³ in the ground, or 444.45 loose yd³ once dug — 32 truck loads at 14 yd³ each. The loose volume is about 25% more than the bank volume, and the truck count is based on the loose figure.

Why is rock excavation so expensive?

Because it needs a breaker, a ripper or blasting instead of a bucket, and the machine time roughly doubles. This calculator uses a ×2.0 multiplier for rock, inside the published ×1.5-×2.5 band; blasting is an extra line on top.

Is excavation billed by the yard or by the job?

Usually as a lump sum for the whole job, with the per-yard rates used to build the quote. A small job costs far more per yard than a large one because mobilisation and equipment delivery are fixed.