Home›Excavation & Fill Dirt Calculator
Excavation & Fill Dirt Calculator
Work out exactly how much dirt a dig moves — bank yards in the ground, loose yards in the truck, compacted yards in the fill — with the swell factor for your soil, truckloads and weight.
Calculate your excavation
Swell and shrink come from the Federal Highway Administration’s earthwork table (Exhibit 5.1 A): dirt takes up more room once it is dug, and less room once it is compacted back into a fill. Caterpillar’s table gives different numbers for the same soil (topsoil 43% swell, not 56%) — the FHWA figures are used here, and the range is noted below. For a round hole, enter the diameter as the length (width is ignored). Before you dig, call 811 (US) to mark buried utilities.
Your results
How excavation volume works
Every dirt job involves the same pile of soil measured three different ways, and quoting the wrong one is the most common way estimates fall apart.
Bank cubic yards (BCY): length × width × depth ÷ 27 — the soil as it sits in the ground, what the plan shows
Loose cubic yards (LCY): bank × (1 + swell %) — the same dirt after digging, what fills the trucks
Compacted cubic yards (CCY): bank × (1 + compacted change %) — what loose soil shrinks back to when re-placed and compacted
Fill: bank yards to buy = compacted fill ÷ (1 + compacted change %)
Truckloads: loose yards ÷ truck capacity, rounded up
Weight: bank yards × 1.35 tons (moist earth, about 2,700 lb per bank yard)
The swell and shrink factors are the Federal Highway Administration’s Federal Lands earthwork table (Exhibit 5.1 A): topsoil +56% / −26%, clay dry +50% / −10%, earth and loam dry +50% / −12%, sand dry +11% / −11%, gravel +20% / −8%, shale +79% / +49%, limestone +63% / +36%. Caterpillar’s table gives different numbers for the same soil (topsoil 43% swell, earth and loam 23–25%), and the FHWA itself says its factors vary ±33% — so treat these as planning figures and confirm with a geotechnical test for a big job. The worked example matches Muthler Landscaping’s cut-and-fill calculator: a 40 × 30 ft area 1 ft deep in earth loam is 44.4 bank yards, 66.7 loose and 39.1 compacted, 7 loads at 10 yards.
Worked example
A pit 20 × 15 ft, 4 ft deep, earth / loam, dry:
Bank: 20 × 15 × 4 ÷ 27 = 44.44 yd³
Loose: 44.44 × 1.50 = 66.67 yd³
Compacted: 44.44 × 0.88 = 39.11 yd³
Truckloads: 66.67 ÷ 10 = 7 loads
Weight: 44.44 × 1.35 = 60.0 tons
The same hole as a fill needs 44.44 compacted yards — so you buy 44.44 ÷ 0.88 = 50.51 bank yards, haul 50.51 × 1.50 = 75.76 loose yards in 8 loads, weighing 68.2 tons. A round hole 10 ft across, 4 ft deep, in dry sand is 314 cu ft — 11.64 bank yards, 12.92 loose yards, 2 loads, 15.7 tons.
How much does excavation cost? (US, 2026)
Excavation is priced by the job, not by a catalogue rate — access, soil, depth, haul distance and dump fees move the price more than the volume does. Enter your quoted rates above and this page totals them. These are the numbers that decide the bill:
| Cost driver | What to ask for |
|---|---|
| Digging (machine + operator) | Quoted per bank cubic yard, or per hour |
| Hauling | Quoted per load, by truck size and distance |
| Dump / tipping fee | Quoted per load, by material and site |
| Truck sizes | Pickup ~1 yd³ · single-axle 10 yd³ · tandem 10–14 yd³ · tri-axle ~20 yd³ |
| Weight limit | A 10 yd³ load of wet clay can top 15 tons — trucks cap on weight before volume |
Waste allowance
There is no waste % on this page, because swell is the allowance: the loose yards are already 11–79% more than the bank yards, depending on the soil. Do not multiply bank yards by swell and then add a waste buffer on top — you would be double-counting. If the soil is wet, root-filled or rocky, use the high end of the swell range instead.
Frequently asked questions
What is the difference between bank, loose and compacted yards?
Bank yards (BCY) are the soil in the ground, what the plan shows. Loose yards (LCY) are what those bank yards become after digging — the soil fluffs up and takes more room, and that is what fills the trucks. Compacted yards (CCY) are what loose soil shrinks back to when it is re-placed and compacted, typically about 80% of its loose volume.
How much does dirt swell when you dig it?
It depends on the soil (FHWA table): topsoil +56%, clay +50%, earth and loam +50%, sand +11%, gravel +20%, shale +79% and limestone +63%. Caterpillar’s table gives lower numbers for the same soils, so treat these as planning figures — the FHWA itself says its factors vary ±33%.
How many truckloads of dirt is 44 cubic yards?
It depends on the swell and the truck. A 44.4 bank-yard dig in earth loam becomes 66.7 loose yards, which is 7 loads in a 10 yd³ truck, 5 loads in a 14 yd³ tandem, or 4 loads in a 20 yd³ tri-axle. Always divide the loose yards, not the bank yards, by the truck size.
How much does a cubic yard of dirt weigh?
About 2,700 lb (1.35 tons) per bank cubic yard of moist earth. Dry sand is lighter, wet clay is heavier — a 10 yd³ load of wet clay can top 15 tons, which is why trucks cap on weight before volume.
Can I reuse excavated dirt as fill?
Yes — but it compacts to less than you dug. Earth loam compacts to 88% of its bank volume, so a 44.4 yd³ hole needs 50.5 bank yards of fill, hauled as 75.8 loose yards. Topsoil compacts to 74%, so it is a poor fill material: use it as the top layer, not the fill.